Before & After: How One Conveyor System Transformed a Warehouse Dispatch Operation — ROI in 11 Month
This is a real story about a real plant. We are sharing it because the numbers speak better than any brochure.

━━━━━━━━━━━━━━━━━━
THE SITUATION — BEFORE
━━━━━━━━━━━━━━━━━━
Client: Consumer goods distribution company
Location: Ecotech-III, Greater Noida, Uttar Pradesh
Operation: 6, 000–8, 000 cartons per day dispatched from warehouse ground floor to loading bay at dock level (+1.2 metres)

The problem:
❌ 7 workers manually carrying cartons to dock — each trip 35 metres
❌ Average handling rate: 380 cartons per worker per shift
❌ Physical fatigue causing 3–4 workers per shift to underperform after lunch
❌ 3 workplace injuries in 12 months — two requiring medical leave
❌ Peak season temporary worker costs: ₹1.4 lakhs per month above base
❌ Dispatch completion frequently missed evening truck cut-off by 15–25 minutes

━━━━━━━━━━━━━━━━━━
THE NEO CONVEYORS SOLUTION
━━━━━━━━━━━━━━━━━━
After a half-day site survey and layout study, our engineering team proposed a 3-section integrated system:

Section 1 — Ground floor accumulation:
• 20m × 600mm powered roller conveyor from pick & pack stations to incline feed point
• Variable speed (0.4–1.0 m/s) to match pick rate

Section 2 — Inclined transport:
• 6m inclined cleated belt conveyor rising 1.2m to dock level
• 18° incline, 600mm width, anti-slip cleated PVC belt
• Load capacity: 800 kg distributed

Section 3 — Dock-level distribution:
• 14m × 600mm powered roller line across dock face with 4 zone stops
• Manual divert gates at each truck bay position

Total: 40m of integrated conveyor — designed in 2 days, commissioned in 16 working days.

━━━━━━━━━━━━━━━━━━
THE RESULTS — AFTER
━━━━━━━━━━━━━━━━━━
✅ Manual dispatch workforce reduced from 7 to 2 (supervisor + dock-end operator)
✅ Throughput increased from 6, 000 to 9, 900 cartons/day — a 65% increase
✅ Physical strain injuries: zero in 20 months since commissioning
✅ Dispatch completion: evening truck cut-off met on 100% of working days since installation
✅ Peak season temporary worker requirement: eliminated entirely
✅ Monthly labour saving: ₹1.58 lakhs
✅ Full project ROI achieved: 11 months

━━━━━━━━━━━━━━━━━━
THE NUMBERS SUMMARY
━━━━━━━━━━━━━━━━━━
Project cost: ₹17.4 lakhs
Monthly saving: ₹1.58 lakhs (labour) + ₹0.3 lakhs (temp workers)
Annual saving: ₹22.56 lakhs
ROI timeline: 11 months
5-year net saving: ₹95 lakhs+ (against ₹17.4 lakh investment)

━━━━━━━━━━━━━━━━━━
Thinking about a conveyor investment but unsure of the ROI?
Share your current operation details — our engineers will model the numbers for your specific case. Free. No obligation.

🌐 www.neoconveyors.com

conveyor ROI case study India
warehouse conveyor before after Greater Noida
material handling automation ROI Ghaziabad
dispatch conveyor transformation Delhi NCR
conveyor investment payback period UP India
Jul 27th, 2026 1:41 PM

Keywords